Eldredge Garage Site Work to Start
The Eldredge Garage Lot, located at 365 Main Street, will close to all parking beginning October 23, 2023 in anticipation of the construction of the lot and new visitors center beginning that week, culminating seven years of collaborative planning efforts to improve the site.
The property, purchased by the Town with the approval of Article 4 of the January 23, 2017 Special Town Meeting, was owned for decades by the Eldredge family and once housed a stable and gas station.
The Select Board created the Eldredge Garage Property Planning Committee in September 2017 to examine and make recommendations to the Select Board on the final use of the property after receiving input from neighbors and community members. The Committee reported those recommendations which included the construction of the parking area with electric car charging station; Visitor Center with restrooms, water bottle re-fill and device charging stations; bike racks; and open space to the rear of the property to the Select Board on November 19, 2018. The Committee also recommended paid valet parking at the lot rather than the installation of paid parking kiosks.
Chatham Valet, Inc. has been awarded the contract to operate seasonal valet parking services through a competitive bid process at the lot since 2018.
Catalyst Architects presented preliminary concept designs based on the Committee’s recommendations to the Select Board in 2018 with revisions in 2021 and final designs presented in spring of 2022. Drainage improvements at the site and in the adjacent roadway were completed while the design work was underway.
The Town received an anonymous donation of $1.5 million towards the project from a seasonal resident through the National Philanthropic Trust which was accepted by the Select Board in September 2022.
The former gas station building was demolished, and initial site work was completed in spring 2023.
Eastward Companies of Chatham was selected under the Massachusetts General Procurement Law’s request for proposals process and was awarded the contract for the construction of the project earlier this month.
The parking lot and new building are expected to be substantially complete in late spring, 2024.